Hi Friends,

Just i have changed holiday calender in golden client , but some error is getting,

Work schedule 2 12 03 GENL 01 2015 already exists

New calender means 2015 holiday list i have put after that i am getting error , do i need to change whole configuration only need to change holiday cal

please help ,

I have doing in golden client, once its ok then i need to move testing .

Regards

jagan

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jan 13, 2015 at 12:57 PM

    any update

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jan 13, 2015 at 04:27 PM

    This is most likely a Warning to inform you that the data already exists. you can go ahead and overwrite the Holiday Calendar.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.