RMDATIND Error : M3 327 Operation not possible Incorrect Material type or plant

sanjana_lingras
Active Participant
0 Kudos

Hi Experts,

We are facing error "Operation not possible incorrect material type or plant" while creating MRP view via MM01.

We checked OMS2/OMSA configs..all seems ok.

If PSTAT value for material is KELVG then after execution it should become KELVGD , but this thing is not working.

Let us know any other configs we need to check.

Regards,

Sanjana

Accepted Solutions (1)

Accepted Solutions (1)

former_member183424
Active Contributor
0 Kudos

So you have not entered the value D for the maintenance status ?

It is a kind of allowance for extend view for material master with regards to a plant.

As you are going to extend MRP view for material, then you have to give the value D in OMSA first.