Dear Experts,

I am creating a PO and entering document freight amount and the document was added.now i am

want to create GRPO based on this PO freight amount will not copied and that field will be a grey out.

please give solution for this issue ASAP.

Thanks&Regards,

Vinothraj K

Accepted Solutions (1)

Accepted Solutions (1)

former_member184146
Active Contributor
0 Kudos

and Make sure that your Drawing Method column in the freight setup screen under the following path : Administration > Setup > General > Freight is not set to None.



Regards,

Manish

Answers (2)

Answers (2)

kothandaraman_nagarajan
Active Contributor
0 Kudos

Hi,

If your drawing method is set to None means, the target document not copied with Freight amount.

If you want copy freight from base to targer document, you have choose based on quanity, volume....

You can modify Freight setup - Under Administration---General--Setup--Freight.

Thanks & Regards,

Nagarajan

former_member184146
Active Contributor
0 Kudos

Hi,

     Which Drawing method you are using for freight, try to use Drawing and distribution method with Quantity, if it does not work try to copy from purchase order with customization Option.

Regards,