on 01-13-2015 9:41 AM
Hi gurus
My client has requested a change in the account determination of plant maintenance.See image below
After my research.I have discovered that for the material section,we use OBYC ,on valuation class for GBB.
My question now is on settlement on the labour part .I have searched for the allocation structure ,i don seem to see anything connected to this.I wanted to know where else i have to search for the 416 000 that is being picked for labour.
Regards
rejoice
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It seems allocation cost element. Check the activity type master data in KL02 for the cost element.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Pl go to KA02 and see the CE 416000....what defined in cat of that CE then we can identify where it has been defined
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In your allocation struct source defined from 300000 to 899999 CE
So 416000 is coming within that range
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Seems that this is a assessment cost element. Kindly check 'Assessment cost element' in allocation structure.
Rajneesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.