Date in General task list

Hello team,

By mistakenly we have updated wrong date in General Task list,is it possible to update date in general Task list.

What will be its impact.

Br,

Karan Varshney

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 13, 2015 at 07:46 AM

    Hi Karan,

    You cannot edit the Key date once the Task list is created. You need to re-create new Task list.

    Impact will be, if a Task list Key date is today date, then you cannot use this Task list for past work orders

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 13, 2015 at 08:25 AM

    Greetings Karan,

    The Key Date that you supply when you are creating the Task List is the earliest date at which the Task List is availabkle and can be included in Orders or scheduled in Plans. Therefore, as Maria Terence mentioned, it is not possible to use, or even find it in selection, if a date such as a Maintenance Plan Schedule date is before the Key Date of the Task List creation.

    It is a good practice to input an earlier date when you are creting Task Lists for PPM purposes, e.g. the start of the previous year, or the start-up date of the technical asset or installation.

    If you have Task Lists for which you need to set an earlier Key Date than initially created, you may create a copy of the existing Task List (specifying the earlier Key Date), then delete the original Task List in IA25.