What does distributed budget in negative mean?

Former Member
0 Kudos

Hi friends,

When I am accessing budget reports (S_ALR_87013559) in distributed budget column some of the value are coming in negative, what does it mean?

Can anybody help me out

Thanks & regards,

varun

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Varun,

inconsistencies sometimes occur due to the hierarchical structure of projects

can you start by running transaction CJEN and see if this corrects this issue?

let us know if that has made any difference

thanks and regards,

c

Former Member
0 Kudos

Hi gooliman,

I have tried CJEN but it doesn't make any difference still facing same issue.

Regards,

Varun

Former Member
0 Kudos

Can you scroll Right to confirm overall values .

& Select the WBS and select Business Transaction.

Message was edited by: ksv ksv

Former Member
0 Kudos

Hi Varun,

Please refer below SAP notes if can help you.

76784 - Incorrect Budget Distributed Values for Project

137619 - Negative budget after budget carryforward

Regards

Tushar

shareeq_hussain
Active Participant
0 Kudos

Varun,

It would be great if you paste a Screenshot or some sample data.

Regards,

Shareeq

Former Member
0 Kudos
MTerence
Active Contributor
0 Kudos

Hi Varun,

Can you please check CJI1, to see the budget entries ? It seems to be an entry from previous year.

Regards

Terence

Former Member
0 Kudos

Hi Terence,

I had checked CJI1 as suggested by you, i found that document was posted in year 2014 and currebt fiscal year but how can it affect the distributed budget?

Regards

Varun

varshal_kachole3
Active Contributor

Hi,

Please follow the steps below:

  1. Transaction SA38-->BPDIST03
  2. Transaction CJEN
  3. Transaction CJBN.

Please report the results once done.

Hope it Helps!

Thanks and Regards,

Varshal Kachole

MTerence
Active Contributor
0 Kudos

Hi Varun,

This can occur due to the low level WBS element are posted with one negative value. On calculating to the top if this is more than positive values, this will result the negative value in top level. This is due to calculation.

Have you executed the report BPDIST03 mentioned by Varshal earlier.

This particular report is to reconstruct the distributed budget values, may be this can solve your issue.

Do run all the 3 reports and let us know if its corrected

Regards

Terence

MTerence
Active Contributor
0 Kudos

Hi Varun,

Check whether the Child WBS elements have any negative budget in CJ30 / CJ31.

Regards

Terence

Former Member
0 Kudos

Hi Terence,

I have Checked CJ31 there is no negative budget

In CJ31 In distrubted column it showing positive value for particular WBS element and for lower level wbs element.

But when I am accessing report 13559 it showing negative.

Regards,

Varun