Hi friends,
When I am accessing budget reports (S_ALR_87013559) in distributed budget column some of the value are coming in negative, what does it mean?
Can anybody help me out
Thanks & regards,
varun
Hi Varun,
inconsistencies sometimes occur due to the hierarchical structure of projects
can you start by running transaction CJEN and see if this corrects this issue?
let us know if that has made any difference
thanks and regards,
c
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Varun,
Please refer below SAP notes if can help you.
76784 - Incorrect Budget Distributed Values for Project
137619 - Negative budget after budget carryforward
Regards
Tushar
Varun,
It would be great if you paste a Screenshot or some sample data.
Regards,
Shareeq
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please follow the steps below:
Please report the results once done.
Hope it Helps!
Thanks and Regards,
Varshal Kachole
Hi Varun,
This can occur due to the low level WBS element are posted with one negative value. On calculating to the top if this is more than positive values, this will result the negative value in top level. This is due to calculation.
Have you executed the report BPDIST03 mentioned by Varshal earlier.
This particular report is to reconstruct the distributed budget values, may be this can solve your issue.
Do run all the 3 reports and let us know if its corrected
Regards
Terence
Hi Varun,
Check whether the Child WBS elements have any negative budget in CJ30 / CJ31.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.