Hi Guys!
I created an organizational structure in the test tenant.
As cutover activity i copied the same organizational structure in the PRD tenant and after all the project activities we set up the Go Live(Q Gate).
I mean the operation is running normaly in the production enviroment.
The problem is that the company created a new services organizational unit.
My question is: Can i create a new organizational unit directly in the Prd system or i have to create a new Project?
Kindly Regards.
Abilon Neves
Hi Abilon,
Yes you can directly create new Org unit in Prod, its a master data, no change project is required in this case.
Regards,
Shobhit