BAPI/FM to change schedule lines in sales contract(VA42)

Hi All,

My requirement is to change quantities by adding reduced rejection quantity & reason for rejection in schedule lines of a sales contract using BAPI/FM. I have searched BAPI's

BAPI_CUSTOMERCONTRACT_CHANGE and BAPI_SALESDOCUMENT_CHANGE but couldn't find fields to update item number, quanities(cumulative order quantity, reduced rejection quantity) etc..

Please suggest the BAPI suitable for my requirement.

Thanks,

Gowrinath.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 13, 2015 at 09:10 AM

    Hi,

    You should try with SD_SALESDOCUMENT_CHANGE with BUSINESS_OBJECT       = 'BUS2034' (used in BAPI_CUSTOMERCONTRACT_CHANGE).

    You have acces to reason for rejection in ITEM_IN table and schedule lines in SCHEDULE_IN.

    Regards,

    Jarek