HI,

Currently all the activities are done in production system and now we want to sync DEV -> QA -> PRD systems, once the sync-up is done we wanted to go for full fledge transport for the above landscape.

Given this scenario we would like to know what are the implications when transports are the being carried out.

Currently we are using BPC 10.0 NW.

Thanks

RK.

Accepted Solutions (1)

Accepted Solutions (1)

bishwajit_das
Active Contributor
0 Kudos

Hi,

As you mention all the activities are done in PRD, then you must take a UJBR backup of the PRD system and restore the same in DEV and QA. Then only you can have a sync of DEV -> QA -> PRD to go for transport .

Wish that helps...

Regards,

Bishwajit

Answers (1)

Answers (1)

Shrikant_Jadhav
Active Contributor
0 Kudos

Hi Krishna,

If you are talking about BPC object transport form DEV -> QA -> PRD  then you need to follow standard   transport mechanism.

Kindly go through the following link

http://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/10947137-aadd-2f10-7b93-82ffed277...

Shrikant