Hide activities 4-6 in prod.ord confirmation

Hello,

In addittion to the activities we use today, in the work center, we want to use activities 4-6 during production order confirmation.

We don't want the user to see it, we will update these activities via BAPI.

I tried to hide all the relevant fields for these activities, through CO86, but found only ILE04-6, ISM04-6, LEK04-6.

The problem is that I still see activities description (TEXT4-6), confirmed activity (RUM04-6), planned activity (SLM04-6), etc..

Maybe someone knows how to hide these fields also?

Thanks a lot,

Yael.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jan 12, 2015 at 11:42 AM

    Barak,

    Try with OPK0 configuration under default tab under services you can see Activities 1-6 hide 4-6 and see if that works.

    BR
    KK

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Yael,

      The activity confirmation details are listed under "services" tab, and is termed as "services" when it is activated / translated to English.

      But, the feature you are looking for is over here itself. As Kiran mentioned, the activity can be hidden by doing check/uncheck as show below:

      Once done the screen skip 4th activity and will look like:

      As mentioned you can edit the text.

      Thanks

      Prem

  • Jan 12, 2015 at 01:26 PM

    Hi,

    You need to use the Transaction Variant in TCode : SHD0 for CO11n.

    The Below Document has detailed process related to same. This would be useful for your query.

    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/40d1443e-0184-2c10-c68d-c612f771fe6f?overridelayout=t…

    Please close the thread by selecting the helpful answer.

    Regards,

    VVJ

    Add comment
    10|10000 characters needed characters exceeded

    • Hi,

      The problem with SDH0 is that I already have a lot of interfaces and other things regarding CO11, so I don't want to create another transaction for this purpose.

      Thanks,

      Yael.

  • avatar image
    Former Member
    Jan 13, 2015 at 08:45 AM

    Hi @Yael Barak,

           CO86 settings will not work for transaction CO11N. Have you tried the option which is suggested by kiran kumar? What you seen in CO11N after activate the hidden check box for your activities 4-6 in OPK0?

    Please refer below thread which is suggesting the note for why CO86 setting is not worked for CO11N.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Sankar,

      I can see that in CO11N I cannot see the planned quantities and hours, and also cannot see the quantity and hours that I've already confirmed (as I can see in CO11).

      It's a data which helps us a lot, do you know why it is not displayed in CO11N and if there is a way to see it through CO11N.

      Thanks alot,

      Yael.