rounding value mismatched when generating schedule line via MRP

when system runs MRP, it generates 13pc schedule line, but the rounding value is 12 in material master MRP view 1


I have checked the change log for SA and material, no change happened on that period.


as far as I know and I also test to prove it:


if the round value is 12 in material master, when running MRP, it should generate 12pc or the multiple of 12 schedule line instead of 13pc.


could any expert help on this? thanks a lot for your help in advance.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jan 12, 2015 at 08:41 AM

    Hi Both, please kindly find the snot


    1.png (49.2 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Caetano Almeida

      Hi Caetano,

      thanks for your info, my customer said it's the first time to get this error, so we will continue monitoring it if happens again.

      I also raised to SAP, will update if any progress.

  • avatar image
    Former Member
    Jan 12, 2015 at 06:43 AM

    can anyone resolve my problem?

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 12, 2015 at 07:23 AM

    Hello Eric Li,

    Could you please provide the snap shot of material Master MRP 1 View?

    Regards

    Gopinath R