Hi All,

We have a requirement where we get 1 HU with example 30 qty in inbound delivery and need to convert them into different HU's  with 1 qty .

Using POSC , we are able to keep the initial HU into deconsolidation area. Now we need auto deconsolidate the initial HU to different HU's as no user will involve in the process.

I request you inputs regarding how to automate this process.

Thanks,

Srikanth. A

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 11, 2015 at 09:58 PM

    Hi Srikanth

    you can do via POSC but not via Decon.

    As for decon system should follow below rule.

    But in your case you have single mat and no diff decon group. So you need to do this via repacking.

    and automate packing.

    No in ur case you can do inbound packing as well.

    Means when you receive IBD in EWM. Run pack program via pack spec and do repacking from 1hu to multiple.This will fix ur issue.

    Regards

    Suraj

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Suraj,

      Thanks for your inputs.

      Firstly we have multiple materials in one source HU. But single material with 1 qty in final HU. So final HU's will be number of total qty of source HU.

      As per two options, we have  via done repacking but how to do auto repacking . .

      Regarding inbound packing , what is that pack program and how can we automate this other than background job. Because use wants run time conversion and automatic.

      Thanks,

      Srikanth.A

  • Jan 13, 2015 at 05:21 PM

    Hi,

    "Using POSC , we are able to keep the initial HU into deconsolidation area. Now we need auto deconsolidate the initial HU to different HU's as no user will involve in the process."

    Why do you bring the HU to a work center, if you do not want to have a user to do anything?

    And what do you want to do in the physical world? You want each piece in one HU? And they are already and you just need the numbered or you really need them repacked?

    Brgds

    Juergen

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Juergen,

      Your questions are valid .

      'Why do you bring the HU to a work center, if you do not want to have a user to do anything?'


      We just need to divide full HU example MAT1 , 10 QTy

                                                                    MAT2 , 5 Qty   into total 15 HU each having 1qty.


      We want it either before GR or after GR using work center.



      Reason why we want in different HU of each qty is because we are implementing EWM AFS and in our scenario we have 1 million different product and batch combinations.


      Due to huge stock , we have faced performance issues . In order to avoid it , we want to put in HU.


      There is no standard in EWM w.r.t our EAN Scanning due to AFS. So we mapped EAN inside HU with each piece.


      So our basic purpose is to keep every piece into one virtual HU to improve performance due to huge stock . That is the reason why no user is involved while splitting the source to destination HU.


      Please suggest can we do auto repack before GR or after GR.


      Thanks,