GR not generate Inbound under Handling Unit-managed SLoc

Hi,

I have a question with regards to HU management. May I know if, under standard SAP, that an Inbound delivery will be created automatically when posting a GRN against a purchasing order into a HUM-managed storage location?

If this is true, I wonder what I miss out on my system because there is no inbound delivery generated. See below my system posting and configuration.

A) System configuration:

B) Transaction.

Purchasing Order:


When trying to perform GRN against this PO item 0020, the following error appears.

Why system does not allow me to post GRN to generate inbound delivery?


Next, I tried another way, by removing the confirmation control key in the PO. However, system complained about missing confirmation control key. However, before the error message appear, I can see the message bar at the bottom showing “delivery being prepared”.


Any idea what is missing?

Regards,
Tuff




c2.jpg (52.3 kB)
P1.jpg (125.6 kB)
P2.jpg (103.6 kB)
Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 10, 2015 at 10:39 PM

    If you have a confirmation control key in your PO which requires an inbound delivery, then you need to have this inbound delivery before you can perform a GR.

    This is usually send by EDI from your vendor to you and you post the receipt from the IBD.

    Confirmations from the Purchasing Viewpoint - Purchasing (MM-PUR) - SAP Library

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Daniel,

      Hope you are doing good. Were you able to find a solution for the confirmation control key error in MIGO while performing the goods receipt against outbound delivery. I'm also in the same situation where we are having an STO------>out bound delivery PGI'ed---------> now trying to do the goods receipt against outbound delviery into a Handling unit managed sloc and at this point get the error that the PO does not contain the confirmation control key.

      Any ideas?

      Thanks in advance for your help.

      Thanks

      Ravi