SNP Planned order and Purchase Requisitions fixed

Hi,

SNP -Heuristic run always creating the PP-Firmed planned orders and Purchase Requisitions. I referred the SCN many posts, no one answered clearly.

Scenario is below.

Master Data:

Product - A - BOM Header

Product - B - BOM Component

Master Recipe


Transferred to APO, SNP and PP/DS PDS generated, If i run the SNP Heuristic run planned and purchase requisitions created with PP-Firmed indicator.


I tried to change the firmed indicator manually in interactive planning boom and Product View, system not allowing me to change.


SNP Planning horizon - 10 days

PP/DS planning horizon - 10 days


Later i changed the planning horizon still orders are firmed.

Is SNP-Heuristic standard functionality will create all requirements a Firmed?

My requirement is - SNP- Heuristic should not create the Firmed orders.

Regards,

LV

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 09, 2015 at 02:55 PM

    Hi,

    As per my knowledge Planned orders / purchase requisitions created via SNP interactive planning to be fixed, this is a SAP standard functionality.

    Is there any way to unfix via User Exit or BADI.

    Thank you,

    LV

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 21, 2015 at 04:47 AM

    Hello,

    If you check the F1 help of PP-Firmed field, you'll get the following:
    "

    The system automatically sets the status PP-firmed

    • if the availability date of the order is within the planning time fence,
    • if the order is a Supply Network Planning order that is outside the SNP production horizon,
    • if the order has one of the following statuses:
      • output firmed
      • input firmed
      • date fixed

    "

    As you can see, PP-Firmed is always set for SNP planned orders when they're generated by heuristic because they're outside SNP production horizon.

    Please make clear the concepts of "Firmed" and "Fixed". I think you (sorry, as well as Satyajit) confused the concept of the two. "Fixed" is used in SNP, which is set for a manually created/change order, while "Firmed" is a PPDS concept.

    SNP heuristic will not delete any "fixed" order but it will ignore "firmed" indicator. Unfixed SNP planned order will anyway be deleted by SNP heuristic no matter whether PP-Firmed is set.
    The purpose that "Firmed" indicator is set for SNP planned orders is to prevent PPDS planning re-planning these orders. You can also see this point in the above mentioned F1 help.

    Hopefully this is clear to you.

    Best Regards,
    Ada

    Add comment
    10|10000 characters needed characters exceeded