Former Member

ME6H report is showing the value "0" for on time delivery


We have Vendor Evalution process in our system. When we run the report ME6H ,the score against a perticular vendor is showing "0" for the period 10/14 to 12/14. We have checked the GR documents for this perticular period against the same vendor for this perticular period & all are showing on time delivery, means the GR posting date & the statistic delivery date both are same.

When we checked the same report ME6H for the earlier period 06/14 to 09/2014 for the same vendor we are getting 100 score.

Would anyone please exaplain why is this happening & what is the logic of periods in the reports.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 09, 2015 at 03:17 PM

    do you have purchase orders in that period or only receipts?

    Add comment
    10|10000 characters needed characters exceeded

    • if the PO is created in 06/14 and the GR is posted in 08/14, then the statistics are posted to 06/14. if you select then 08/14 as period for ME6H then you will see 0.

      If you don't agree, then post a screenshot of your S013 and screenshots from ME6H according to your findings in the initial question