on 01-09-2015 10:13 AM
Hi,
In the SRM System, SC is created with a requester XYZ and BP 1234. Later the User assigned was changed in the Organization structure as a result new BP 2345 was created for the user XYZ. Now how to replace the new BP with Old BP number?
Hi. I have a feeling there may be something in SRM 7 EHP 3 to assign docs from 1 BP to another also.
Regards,
Dave.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please user Report Z_CHANGE_PGUID_002--SRM5.0
Or
Z_CHANGE_PGUID_003--SRM7.0 and above
attached in notes 1507030 & 1706323
to replace corrupted BP in open documents
Best regards,
Ivy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI ,
In Order to Change the BP number in existing created SC and also in order to display those sc in worklist of new user. You need to create custom Abap program.there is no standard.program or function module for this.,
Regards,
Sanjeev.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.