Actual and Commitment Cost of a WBS

From Which table i will get Actual and Commitment cost of a WBS.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 09, 2015 at 06:16 AM

    Hi Shailendra,

    For Plan Cost of individual WBS; we should pass WBS as input to PRPS-PSPNR and obtain the PRPS-OBJNR.


      After fetching the PRPS-OBJNR, pass this value to RPSCO Table, RPSCO-OBJNR with value type RPSCO-WRTTP = 1 and get Plan cost for WBS by adding the value obtained in the following fields of RPSCO table WLP00, WLP01,...to.... WLP16.

    Also find the below link

    Planned Cost and Budget - RPSCO Table Details - Product Lifecycle Management - SCN Wiki

    Regards

    Rajkumar Narasimman

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Rajkumar,

      I am not getting acutal and commitment cost.

      Is there another way available ?

      Regards

      Shailendra Karada