Precalculation SAP Server Capacity before deploy Roll Out Project

Hello Experts,

Kindly any one share your great experience to help our requirement.

We are planning to implement new business scenarios and new client in existing Production server.

Before deploy new business functionalists, what are factors need to consider in existing Production server.

How to precalculate SAP server capacity to adopt new functionality, how affect workload, performance, memory..etc..

Kindly any one the list of factors.. and some standard document.

Regards,

Karthik

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 13, 2015 at 02:02 PM

    Hi Karthik,

    First find out the 'capacity' of your current server hardware. Ask the HW provider for the SAPS number of the machines, or look it up on SAP's benchmark sides http://service.sap.com/benchmarks

    Then monitor the current usage of your servers to find out how many SAPS you need for the existing functions, and how much headroom you have left.

    And for the new functions, look whether some sizing guideline exists (http://service.sap.com/sizing) or if a sizing for the new application is implemented in the quicksizer tool.


    With that, it should be a simple a + b = c type calculation.

    Best Regards, Randolf