How do I remove components from a production order pick list?

Our assembly line prints a pick list before final confirmation of our product.  Only a few ROHs are required on this list. However, all HALBs are listed on the pick list as well.  This confuses the Assemblers so I would like to remove them.  The only help I have gotten internally is that since we did not allocate components to operations, they were defaulted to operation 010.  If I change the HALBs to operation 020 via CA02, it will not change the pick list, correct?

Thanks,
Jay

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 08, 2015 at 06:40 PM

    Hi Jay

    If the backflush indicator is set the material should not appear on the picklist.

    BR

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

    • This tells me that we can change the component allocation, which will add/remove items from the pick list (since every item on the pick list has operation 010).  If I change it, will it be removed?  If it does, are there any other concequences.

      Jay King,

      Please remember component allocation to different operations determines same components during order operation confirmation.

      Suppose if you have assigned all components to operation 0010 and Back flush indicator set in material master then during order confirmation for operation 0010 you can see all components were listed in goods movement tab.

      If you assign component allocation to second operation then those components would listed during second operation confirmation.


      So with changing the component allocation you can not drop your assemblies from printing so only option is find out the smart form for your pick list in OPK8 and Exclude required components from printing with custom logic.

      BR
      KK