We are trying change WBS status from PARTIALLY CLOSED to RELEASED TOTAL, when we received this message:
CJ672 - Master data WBS element C14\00xxx is blocked.
CAUSE
WBS element C14\00xxx is locked. You cannot change any data.
WHAT_TO_DO
You can unlock WBS element C14\00xxx using the menu.
Somebody had this problem?
How get unlock WBS element through this Menu?
Which way to this menu?
Best Regards.
Hello Guys;
@Gabriel Izoldi;
When user tried Edit > Status > Unlock > Master data, System show us message:
User status partially closed is active
@Tushar
I checked this note but I don't found some solution that can be used.
@Ken;
I'll ask user try it.
Thanks a both.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Partially Closed means that a lower level WBS is closed. Navigate down to the lower level WBS that is closed and reopen it.
EDIT -> STATUS -> CLOSE -> UNDO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ricardo,
Please refer following SAP note
544400 - Lock WBS element: Error CJ824 with processing of AuC
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ricardo,
Have you tried Edit > Status > Unlock > Master data ?
Regards,
Gabriel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.