ISBD is in Active for W.B.S.E . How to Deactivate ISBD

Hi All,

The problem for W.B.S.E, ISBD is in active in production client when I tested in development it is same

in development I tested as below scenario

Ex: current budget for a project is Rs1000

PR done for  Rs1000

PO done for  Rs1000

MIGO done for Rs1000

MIRO done for Rs1000

the budget is not exceeded to given budget for a project  but ISBD status is in active WHY?

Regards

Ambarish

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 09, 2015 at 03:42 AM

    Hi Ambarish,

    You may check the explanation given in SAP note 1045796

    Please perform transaction SE38, type in Program = SAPLBPFC and execute menu path 'Program -> Generate'.

    Regards, Gordon