Skip to Content
avatar image
Former Member

Planning callendar


Hi Experts

I have got some doubts about planning calendar. If the  factory calendar is set  with Saturday and sunday as holidays ,

is the same setting could be applicable to Planning calendar ? If so if I want to violate this , how to achieve this?

    Second question is if I want to set first three days of each week as working days in a planning calendar , how to define calculation rule

to achieve this?

Thanks in Advance for clearing above doubts

Regards

Srinivas.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 08, 2015 at 11:33 AM

    Hello Srinivasrao,

    Planning calendar depend on the factory calendar. Whenever changes in  factory calendar, planning calendar need to be updated.

    • Again in planning calendar have some special future '

    See below picture

    Ex. Period fall on day which holiday in that case system provide the above option:  consider the following day, Previous day, and in "No new Period day" system not create any period and "DO not Displace" ( consider a same day) in planning calendar period.

    Select one of the option as per your requirement

    • If you want to calculate the first three day as working day in planning calendar

    Create the calculation rule like as below

    Select the Rule : Weeks (week Days)

    Enter : 1, 2,3 ( In this case system consider the every week Monday, Tuesday, Wednesday)

    you can select any day with in week


    But on particular day period fall on holiday system then system create new period with above logic


    Please check and confirm the same


    Thanks  &  Regards

    Umesh Mali  


    PP_UM.JPG (14.7 kB)
    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Umesh Mali

      Hi Umesh

      Thank u very much for giving me the valuable inputs.

      I have got understanding about my requirement.

      The document provided by caetano is also helpful.

      shall u also provide me suggestions on Layout definition of Pi sheets which is posted in another        thread ?

        I am closing this thread with correct answer.

      Thanks and Regards

      Srinivas.


  • Jan 08, 2015 at 10:52 AM

    Hi Srinivas

    No, the planning calendar will not override a holiday defined on the plant factory calendar. MRP will always consider the working days according to the plant factory calendar and there is no alternative to change this.

    Regarding the second question, just define a weekly period and set weekdays 1,2 and 3 on the calculation rule.

    See the following document for details.

    How Planning Calendar Works

    BR
    Caetano

    Add comment
    10|10000 characters needed characters exceeded