To determine the Date of TECO for the Production Order

Dear Experts

I seek to know the logic to determine the date when the Production Order was TECO 'ed (Technicaly Completed).

The order can be made TECO and revoked on more than one occassion. How do we ascertain the date of the  execution of last TECO status.

With Appreciation, Thanks & regards

Ayaz

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Jan 08, 2015 at 08:01 AM

    Khan,

    In CO03 go to header from menu bar then select status changes under which you can see details for TECO status which has been set last time.

    BR