on 01-08-2015 4:44 AM
Hi gurus,
Currently i am mapping a chemical industry project.
here i have to map consumable products to work centers.
EX- suppose for 10 ton of fished product they are using 10 bags and 10 pallets.
they want to make a track of consumable bags & pallets.
stategy MTS, Industry- PI,
I have made a planned order of 10 ton, for each ton 1 bag & 1 pallet have to consume automatically at work cener.
Si how to mapping this ?
please help me in this regard,
thanks in advance
Hi Shiva,
As per your question If it is automatic assignment of bom component to particular workcentre & consumption automatically at the time of confirmation, then...
go to routing & select operation then click on component allocation.
After that system ll show U all bom component, select required component assignment to this operation & then click on assign button.
Pls check & confirm
Thx
Alok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.