Dear All

We run MRP based on the PIR quantity updated in MD61. Now I see that if I run the MRP say on 7th Jan and my PIR is for 1000, in MD62 it considers only 800 for planning and displays 200 as withdrawn qty. But this 200 was withdrawn for last month plan, but it has been done this month. How do we control this so that system considers 1000 as plan.

Secondly I see that for few materials only withdrawn quantity is displayed and for few it is not displayed. What may be the reason for this.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jan 08, 2015 at 07:54 AM

    Can you show us the snap shots for PIR withdrawal dates,DM screen for schedule lines and MD04?

    BR
    KK

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      The PIR was created through a BAPI. So in this case, it will consider the withdrawal quantity.

      The note 144513 helped i solving this. thank you for support,

  • Jan 08, 2015 at 04:35 AM

    Adithya,

    Check your Planning strategy and Consumption mode and period days for different materials.

    BR
    KK

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 08, 2015 at 07:19 AM

    Hi All

    Do we have any inputs for this.

    Add comment