Hi ,

I am using PPM 5.0. PPM item integration with SAP PS project. I am planning to update planned/actual work hour from PS project to PPM item Capacity Planning.

I have maintained the proper setting like Cost element mapping to capacitu categoty, capacity group and view. Capacity view is set as integration. PPM item has object link with PS WBS. The Global setting also maintained.

When I use the report /RPM/FICO_INT_PLANNING, it does not update the capacity planning view from PS project. But Finance view is updated properly.

Is there any extra setting needs to done?

Thanks,

Morshed

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Jan 11, 2015 at 02:27 AM

    Try running older program /RPM/CAP_PLAN_INT in foreground for the transfer - it has more explicit error messages if there are any. Assuming that you have the FI integration running, there may be an issue with data mapping to proper capacity views & categories.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.