Hi Experts,

I have a issue with budget error with one of the project.

In report S_ALR_87013558, Assigned budget of 498 is shown on the WBS element CV/0017-2-01-02-01-01-06 but in CJ30 and CJ32 the same value is shown on the higher level WBS element CV/0017-2-01-02-01-01.

I have run CJEN and then CJBN but still the difference remains.

Kindly help me in resolving this issue.

Screenshots attached for reference.

Best regards,

Shynu John

S_SLR_87013561.PNG (66.6 kB)
CJ32.JPG (128.6 kB)
CJ30.PNG (63.8 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jan 07, 2015 at 09:00 AM

    Hi Shynu,

    Can you release the 6500 OMR which is available in CJ30 but not released in CJ32 and then reconstruct the database using CJEN and CJBN.

    Let me know how it goes..

    Regards

    Sammar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 07, 2015 at 11:38 AM

    Hi,

    Plz check in CJ32 on mentioned WBS whether same amount in Current budget exist or not, If it exist than select that WBS element  and go to edit->copy view->current budget-> select 100% . after this select all WBS element than go to edit->total up and save it. Hope it will resolve your issue.

    Thanks.

    Add comment