MTO - get finished goods receipt to post at EK02/sales order costing price?

Hi All

I Have a MTO process, the standard price of the FERT is 10 in material master. Total of the bom or sales order costing estimate is 7. Why when I GR Finish product it post a value of 10 not same as sales order estimate price (7) ?

How to I get it post at the EK02 or sales order costing price? and as standard sap which is correct? standard price in material master or EK02 price?

Thank you all

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 07, 2015 at 06:35 AM

    Hi,

    You have to check the requirement class, it has the costing id as B and Valuation should be M. Then only system will post GR with sale order price i.e. EK02 price.

    Regards,

    Mukthar

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 07, 2015 at 05:00 AM

    Hi

    1. GR is always valuated at price/cost updated in Material Master...so system rightly doing

    2. Codition EK02 is a statistical posting used for pricing procedure