CRM Java Upgrade 6.0 to 7.02 MOPZ Issue NW target is current 7.00 SP21

Hi All,

I performed dual Stack Split in CRM 6.0 in preparation for CRM upgrade to 7.02. After split with separate DB for ABAP and JAva, I tried to generate XML for upgrade. MOPZ is showing target for ABAP CRM perfectly 7.02/NW7.03. On the Java side, Target is showing as 7.02/NW 7.00 SP21 which is current NW level. Please advise what could be wrong and how to fix and generate XML with correct Target. SLD is pulling all Java side components correctly after SLD reconfigure.

Thanks,

Kavitha Rajan.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 06, 2015 at 11:14 AM

    Hi Kavitha,

    What the version of Solution Manager system?

    Try to re-configure CRM Java.

    Your target should shows below CRM Java versions

    • SAP BS 7i 2011 Java (CRM 7.02 JAVA on NW 7.4 , CRM 7.02 JAVA on NW 7.31, CRM 7.02 JAVA on NW 7.3, ERP 6.06 JAVA on NW 7.4, ERP 6.06 JAVA on NW 7.31, ERP 6.06 JAVA on NW 7.3, SRM 7.02 JAVA on NW 7.4, SRM 7.02 JAVA on NW 7.31 & SRM 7.02 JAVA on NW 7.3)

    You can select any of one NW 7.4 / NW 7.31/NW 7.3 as per your customer requirement.

    Regards,

    V Srinivasan