CHANGE_MDPSX_MSSL and MD_SUBCONT_LOGIC

Hello

May I know what is the different between BADI MD_SUBCONT_LOGIC and the method of CHANGE_MDPSX_MSSL under BADI MD_CHANGE_MRP_DATA?

It seems if I want the SAP MRP to consider Subcontracting Stock (i.e. generated via movement 541) as part of available stock during MRP, I can make use of either of the above BADI, but which one is the correct BADI to achieve this?

Using MD_SUBCONT_LOGIC has a downside in which if I want to switch to Simple logic it has the following implication:

This logic is generally of use for components to be provided that are specifically assigned to one subcontractor. If several subcontractors are involved, this has the undesired effect that in planning, the stock of material provided is drawn from a distant vendor to cover another vendor's requirement of material provided.

As such, may I use BADI MD_CHANGE_MRP_DATA  of method CHANGE_MDPSX_MSSL to achieve this requirement?

Please refers to a forum (http://scn.sap.com/thread/1440341)

Regards,

Tuff

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Jan 05, 2015 at 04:06 AM

    Dear Daniel,

    1. BADI : MD_CHANGE_MRP_DATA

    Kindly refer the following Note 190298.

    2. BADI : MD_SUBCONT_LOGIC

    If you want to consider the Stock provided to vendor for jobwork (541) also into MRP then you need to use this Badi.

    Regards,

    Karna J