Capacity leveling job error

Hi All,

I am getting the below error while running the capacity leveling job.

Unknown characteristic combination 82152/4410/WH_PCDC-1_4405_001

where 82152 is a product,4410 is location and WH_PCDC-1_4405_001 is resource.there are other products for which its runing fine over the same resource.

I have run the consistency and OM17 but still getting the error.

Thanks,

Krishna

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jan 02, 2015 at 02:26 PM

    Hello Krishna,

    Can you please check if the CVC is maintained for this product in /sapapo/mc62.

    -Thanks

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 03, 2015 at 09:05 AM

    Hi Krishna,

    I believe, the time series data was not created for the combination. Did you create this material manually in APO? If so, then you need to assign the material, to the model first. Then re-initialize your planning area for the version.

    Even if you didnt create anything manually, I suggest to re-initialize your planning area before you take the capacity leveling run.

    This should resolve your issue.

    Thanks,

    Satyajit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      OK. In that case please delete the pln ord (created by heuristic/optimizer) and run the PA initialization job. Then re-create the pln order by taking the heuristic/optimizer run. This time you should be able to take your capacity leveling run successfully.

      If this doesnt work, then you have to delete the location-product in APO and then re-cif it. After that do your planning.

      Thanks,

      Satyajit