How to move "Payday" a day before PH

Hello Friends,

I have defined Paydays thru program RPUCTP00 in SE38 table. please help me in defining the payday as last day of the month, in case last day of the month is falling on Day Off or Public Holiday so how can i move my payday a day before day off/holiday?

Thank you

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Jan 03, 2015 at 08:55 PM

    If you go through the IMG to generate your Payroll Periods, you should be able to see the 3 Nodes to "Generate payroll periods", to "Check payroll periods" and to "Check pay dates".  That last one also allows you to modify the PayDate.

    Alternatively, use sm30 to access table view V_T549S_B for Date ID Type 01.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 31, 2014 at 08:40 AM

    Go through below image to generate pay day as last day of the month.

    Regards

    Venkatesh