We have project stock for a considerable amount against particular WBS (In Crores )

This Project stock is not reflecting in CJI3 .

Problem is We had used upload Program for Project stock update and now it seems it didn't update CJI3 dependent table (COVP i think).

How to correct the entries in CJI3 ?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • Best Answer
    Jan 07, 2015 at 12:28 AM

    Are you using Valuated or Non-Valuated Project Stock? With Valuated Stock the costs do not hit the WBS until they are issued to the WBS.

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 07, 2015 at 04:56 AM

    Hi,

    CJI3 report is for displaying actual cost and check what movement you have used by uploading program. if the that is issue to project/wbs then cji3 will display that amount in report.

    check also stock is that valuate or non valuated as ken suggested above.

    Regards,
    Sanjeev

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 07, 2015 at 11:03 AM

    Hi KSV,

    Have you tried executing tcodes like S_ALR_87013558 to confirm whether the values are updated.


    Have you checked in tables RPSCO / COSS / COSP.


    CJI3 will display cost line items based on cost elements. Normally CJI3 will display the cost, but there is some thing wrong. In case if you feel this is an issue, raise a OSS Note to SAP.


    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 07, 2015 at 01:32 PM

    Hi,

    Try CJEN.

    PK

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 07, 2015 at 09:30 AM

    Hi,

    I am bit lost on scenario here, for me the transfer from Unrestricted stock to Project stock is BS to BS account, so no P&L at all. Your material accounts must be defined as cost elements type 90 to reflect in Controlling.

    BR,

    Paulo