Automatic Transfer of Forecast/Requirments for FG

Former Member
0 Kudos

Dear All,

Is there a way of automatic transfer of Forecasting/Requirements from a finished good Item A to Item B once Item A has zero stocks?

Thank you in advanced!

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

On the standard MRP this is not possible.

You can do that using a Supersession Chain, however, your material would be planned by APO. Check the link below for more details:

Supersession Chain - Master Data for Product and Location Interchangeability - SAP Library

The supersession is also available for the industry solution DIMP:

SAP Library - Inventory Management

Otherwise, if you are not using DIMP or APO, you may try to develop your own solution using BAdIs MD_ADD_ELEMENTS and MD_CHANGE_MRP_DATA.

BR

Caetano