Skip to Content
avatar image
Former Member

Unable to enter the COntract end date as blank in spro

Hi Experts ,

I have to set in the schedule condition the contract End date as Blank in spro I have done the changes , but when I try to schedule the action on a contract with blank contract end date the action is not getting scheduled and it seems  there is some issue while setting the blank value , because when I set the date as 31129999 , it is working properly , please suggest .

Thanks ,

Vaibhav

Capture.PNG (2.5 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 30, 2014 at 06:52 AM


    Hi Vaibhav,

    I don't think blank space will work.

    so trigger the condition you can provide between date like to date and from date.So sapce woudn't come in between.

    or you can a new date rule like sapce and assign it..

    If this condition won't work ,then you have to trigger the condition using code,

    Regards

    RR Pradhan

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thank you Pradhan

      Got the solution , actually after entering the space we should not press enter , just save it , it works fine then .

      Thanks ,

      Vaibhav