function module to get budget from s_alr_87013558

Hi,

I want to display some output field of report S_alr_87013558 which are Budget, Actual And Commitment , In an ALV Report.

how can we do this? it there any Function module or any other way available to get the budget from S_alr_87013558 .

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Dec 29, 2014 at 07:05 AM

    Hi Shailendra,

    Check tables BPJA, BPGE for budget, COOI, COSS/COSP for commitment/actual.

    OR check RPSCO for all.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Jul 13, 2020 at 11:57 AM

    Logic

    Pass Input Project Code in Table PRPS Field - PSPHI,It will display all WBS of Input Project

    get object no - OBJNR against each WBS and Pass to table RPSCO include Field Budget Type = KBFR & value key = 45

    and display WBS wise value in Column Budget.

    Actual Cost Logic

    Pass Input Project Code in Table PRPS Field - PSPHI,It will display all WBS of Input Project.

    Step 1- get object no - OBJNR against each WBS.

    Step 2- Pass WBS no in table AFVC - PROJN and get Object no OBJNR

    Now pass Object no of Step 1 and Step 2 into table COEP field OBJNR,display total of column WKGBTR against each WBS.


    zqxcy.png (23.5 kB)
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.