Reg: Defined shift details not shown in CO11N

Dear Experts ,

I have defined shift sequence  ( Two shifts , First and second shift)


But in confirmation screen , i am able to see only in shift (First Shift)


Can any one please let me know , which data is missing.


Regards

shift-1.png (36.1 kB)
Shift-2.png (27.1 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Dec 29, 2014 at 05:04 AM

    Hello Daya,

    Please refer the below document for Shift related confirmation

    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/c0fa9a04-376a-2c10-c396-86d32ac80614?quicklink=index&…

    Also check OSS note 1540803 - CO11N: Incorrect proposal of shift

    Best Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 28, 2014 at 08:50 PM

    Hi ,

    For shift assignment have you maintained shift sequence. It is important to maintain Shift definition, shift sequence and duration of the shift.

    Please check and conform.

    Regards,

    Krishnendu.

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 28, 2014 at 11:46 PM

    Hi,

    It seems you have only maintained the 1st shift sequence in work centre capacity. You can do +Shift and add the 2nd shift as well and check afterwards.

    Thanks

    Prem

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 23, 2015 at 10:11 AM

    Hi thank you all ,

    Closing this thread.

    Valid from date of second shift was not defined correctly in shift definition.

    Issues is resolved.