XML message not triggered for ECC PO MM_SUS

Dears,

I am in ECC 6.0 and EHp6.

I am working in a classic scenerio, where the PO created in ECC are not send to SUS system.

I checked everyconfiguration,

1. Vendor with class type

2. WS53800008 – Class -CL_SE_PUR_PO_WF_OUT   Method – execute.

- Here the WF is completed sucessfully without error.

But there is not XML message generated.

3. impleted the BADI- pur_se_po_interface_out_select.

Seems done everything and checked most of the things.

still the XML message is not generated in ECC.

Kindly help me on this.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Dec 29, 2014 at 04:41 AM

    Hi

    Please make sure your SLD connection are working fine.

    Please run TCODE SLDCHECK and make sure you getting SLD connection successful message.

    If not please ask your Basis consultant to check this.

    Go to tcode SPROXY and check ESR connection are working.

    Also check if you have implemented badi pur_se_po_interface_out_select and if if you have put any conditions . Does that conditions are matching. If not system will not trigger XML.


    Thanks

    Sanjeev.

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 29, 2014 at 08:43 AM

    Hi,

    Would you please check the following points?

    1,

    Please use transaction SWETYPV and search for the entries BUS2012.

    There are two entries, one for event CHANGED and one for CREATED. For

    both entries the type linkage has to be activated for workflow

    WS53800008.

    2,

    Please check if own company was successfully created using

    BBP_SUS_BP_ADM and if suppliers are successfully replicated.

    3,

    Also please check Your entries in table BBP_BACKEND_DEST.(KBA 1846783)

    Best regards,

    Ivy

    Add comment
    10|10000 characters needed characters exceeded

    • I agree with you IVY

      that is one way in MM SUS to send PO

      Refer para in article here

      Flow of SAP MM and SUS Portal

      It clearly says " In the MM-XI-SUS scenario the PO will be created in ECC and transferred to SAP SUS. Depending on ECC release there are two different possibilities for this, either the ECC system sends IDOCs or sends XML messages directly."

      I hope you are clear we are getting issue as XML is not getting genrated in ECC to send the PO in to PI system.

      Kaustubh