on 12-27-2014 8:12 AM
Dear Experts,
I am getting the error while running the CK11N I am able to see the values in kp26 coster/activity, in material master selected quatity structure under costing tab.
Why I am getting the bellow error I don't understand and I don't know how to fix it. Please help me from that.
Regards,
Mahi.
Hi
Forst in CK24 mark the cost estimate and then release
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Great Mahi, you did it !!!
Thread will not be closed this way. Either you have to mark it as 'Assumed answer' or you have to give correct answer to the best suited answer.
The good part you have done is that you have mentioned how you solved it. This helps other visitors if they are stuck some where in the same problem.
Regards
Rajneesh Saxena
Hi Mahi,
Have you assigned activity costs to cost centre structure in OKTZ?
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As I said in my earlier reply, kindly confirm whether you have maintained activity prices manually in KP26 or these are calculated by system through KSPI? If manually maintained then this message is obvious because price indicator at activity master is 1 i.e. price automatic calculation and system is not finding KP06/KP26 and KSPI values.
If that is not the case you need to check note 1872228 as this may be system error also. .
Regards
Rajneesh Saxena
Hi Rajneesh
But if you see the cost itemization it is showing all activity cost properly..
When he is getting this error?
Actually I have tested it without KSPI..it is working with KP26..only no primary cost comp split
So..this error should not come....
I have seen there is no Prod version defined in screen shot
Thanks
Hi
You are right at your place Kamal but I have seen this message long back in my own system and the reason was that system was expecting auto calculation and I was giving manual price.
Secondly if we don't give PV, system takes first PV available with it. This is my observation.
Thirdly it may be a system error also for that I have mentioned the note.
Now we have to wait for OP's response.
Regards
Rajneesh Saxena
Hi Rajneesh,
In kp26 I have maintain price indicator 1 that means plan price automate calculate and I do not i have run KSPI and do not have maintain settings for cost center split in OKES but I am able to see the values in KP26.
Shall I maintain the settings for cost center split OKES.
Regards,
Mahi.
Hi
That is because you have not run KSPI and Plan cost splitting..and directly defined activity price in KP26...
You will only get cost itemization and not CCS actual cost splitting as per attributes defined in CCS.
But your cost estimation showing "Green" is it ?
So..if you want to get CCS splitting...run plan cost splitting KSS4 and then KSPI
Pre-requisite: Cost planning in KP06 & KP26
Hi
Cost center splitting is a different concept and all the time it is not required. It is required only when you have some activity independent planning or actual posting on the cost center. I don't know whether it is applicable in your case or not.
I said/asked one simple thing: Have you maintained manual prices in KP26 i.e you have not maintained KP06 (plan expense) and KP26 (plan activity quantity) and have not done KSPI but you have price indicator as '1' in activity master, in this case this message is obvious becouse system is not finding any values to calculate activity price automatically and at the same time it is finding instruction to calculate activity price automatically from activity type master.
Regards
Rajneesh
Hi
Seems your activity master contains price indicator 1 and you are giving activity price manually at KP26 hence you are getting this message.
Regards
Rajneesh Saxena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Go to Material master costing view and change costing lot size to 1000
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.