Skip to Content
avatar image
Former Member

SAP MD04 Unplnd requirement

Hi

We are using Forecasting, hence once we execute MPR1 they appear as Unplnd requirement in MD04

We don't want them to appear in MD04 as we use MD70 to transfer  and appear as ind requirement

Please suggest how to to stop requirement created via MPR1 as Unplnd in MD04 or is this a standard SAP behavior if forecasting is done they appear as Unplnd in MD04

Thanks

Sankar N

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Dec 25, 2014 at 12:37 PM

    Sankar,

    What is the MRP type you are using?

    If you want to do forecast with MRP like you don't want to see forecast values to show up in MD04 as requirements until you copy them through MD70 then in MRP type configuration in OMDQ MRP Procedure Select D and Re try your scenario.

    BR
    KK

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Kiran Madhurakavi

      Dear Kiran

      These setting when I tried are working when we use  forecasting view model selection not via external ( N ) , so when we do MP30 these setting are used for forecast calculation

      I need help when I execute MPR1 forecast values shouldn't be displayed as unplanned requirement

      Looks like this is a Standard SAP behavior , hence closing thread

      Thanks

      Sankar N