how stastical key figure used on project structure

Hi, can anyone one please explain how to use statistical key figure for project planning and actual cost posting. also I need to know how it will update in backend and impact on project structure(wbs and activity) during execution. Regard, murali k n

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 26, 2014 at 12:06 PM

    Hi Murali,

    Go to forum. there are many topics related to SKF.

    Few of them are:-

    Statistical Key Figure - General Ledger Accounting (FI-GL) (New) - SAP Library

    Statistical Key Figures and Statistical Key Figure Groups - Profit Center Accounting (EC-PCA) - SAP Library

    Example:-

    Basically, if you talk about SKF in terms of a project and that too in terms of a construction, then there are many activities like excavation, PCC, RCC, Re-inforcement, Shuttering etc which can be measured according to their unit of measurement like MT (Metric Tonnes), M (Meter) etc.

    Now, when we plan something in Project. It needs to have its associated SKF. Like for next 3 months you would be doing 90 MT of concreting and against which you will post your actuals. Now,system would calculate your SKF Plan vs SKF Actuals. However, there is also a provision of cancellation of your actuals SKF.

    I would rather suggest you to try in your development/quality client.

    Step1:- use KK01. Create one SKF-Lets say. EXCVNS (Excavation). Put the UOM as MT (Metric Tonnes)

    Step2:- use CJK2. Here, you will plan your SKF for the period defined.

    Step2:- Use KB31N. Here, you will post your actuals against your planned SKF.

    You may also use report S_ALR_87013548 to see the SKF planning and posting distributions.

    I hope this may help you a bit.

    Regards,

    Amit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Amit,,

      Request you to let me know if you have time to provide the online training for on IM budgeting.

      Please reply as it is on urgent.

      Regards,

      Wasim