Hi Experts,
We are using CPS Redwood for Job scheduling .Version is M33.92-68971
Is there any configurtion which can do in CPS so that it will send email to users if a particular job runs for more than specified duration
Say we keep a limit that if any job runs for more than 2 hours and not compelted it should send email to a particular DL
Is this possible
Please suggest
Regards,
Murali
Hi Murali,
You can achieve this through alerting.
Under alerting -->Job definition Alert source->Create new Job definition alerts source.
Fill the required details, Job pattern(U can give job name if the name if no other job name exist with similar pattern)
Under status select running and put delay amount to 2 and delay units as hours.
Create job default alert escalation , alert source email(not required if u already handling alert through alerting gateway)
Regards,
Ravindranath Reddy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Ravi for reply ,i dont see alering module in my system
I belive we need to have seperate license for this .Please confirm
We observed there is one more way ,when you edit job definition you see a tab called Runtime limits
Here you can set the maximum time which job can run and whether you want to kill it if that time exceeds or you can define an Event to trigger alert to specified user group
Regards,
Murali