on 12-24-2014 1:35 PM
Hi Experts,
I posted GR in EWM system and saw that it has not updated in ECC Inbound delivery. After that I saw PPF function and it was in failed status. Later I reprocessed PPF action and it was processed successfully. Still I am not able to post PGR for Inbound delivery. I checked SMQ1 of EWM and there is nothing failed in queue. Also I checked SMQ2 in ECC but could not track update of EWM by any value i.e. ID of EWM/IDN etc. Also I checked SLG1 in EWM where it shows successful log.
Please let me know how we shall track EWM posting in ECC to understand why it has not updated ECC Inbound delivery.
Appreciate your reply.
Thanks & Regards,
Prashant Dhakane
Hi Prashant ,
Is it the first time when you are facing this problem ? I have seen cases in past when system missed to update the GR document in ERP
But before concluding anything , check below things
1) check the EWM material document in MKPF table ? It could be possible that material document is posted but somehow IBD status is not updated..If it actually missing I would suggest you to raise an OSS.
2) SMQ3 , someone might have save that queue
3) Application and system log may give you some hit
By the way can you specify the EWM version you are using ?
Regards
Sandeep Marwha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you use Idoc or qRFC for communication? Can you show log from slg1?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check both, SMQ1 & SMQ2, in both EWM and ECC Systems.
Regards,
Sathish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.