Target cost version for calculation

Dear Experts

when i using Tcode COR3  for process order to read cost under Goto --> Cost --> Analysis. And then selete target cost version. But the defaul is 0. I want to default version 1, how to do it. pls advice. I already defined the vesion 1 for controlling area in OKV6. I also cheked all the following steps.


1. Defining Variace Keys OKV1

2. Define Default Variance Keys for Plants OKVW

3. Check Variance Variants (OKVG)

By default it showing version 0. How can i see by Version 1

Regards

Vishal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Dec 24, 2014 at 11:56 AM

    Hi Vishal,

    In cost analysis screen, Select the version from the menu- Settings - Versions - Target cost version. Here you will get version 1, just select on it. I have also attached screen shot.

    Regards,

    Mukthar