In MD04 I have available quantity in negative, but after MRP run the system not proposing the rescheduling.

Please explain why the system generating the reschduling proposals.

Thanks,

Suresh.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Dec 24, 2014 at 10:54 AM

    Hello Suresh

    You should always use MD05 instead of MD04 to check the rescheduling proposals generated from MRP.

    See the following document:

    Why should I use transaction MD05 to analyze the MRP results?

    If it's not helpful to you, please provide a screenshot of MD05.

    BR

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Suresh

      It looks like system is generating new planned orders on specific dates. Which lot sizing procedure are you using?

      Please also check if there are tolerance values defined for the rescheduling check on OMDW.

      It's also possible to hide an exception message on customizing. Check the rescheduling messages customizing on the following SPRO path:

      MRP-->Evaluation-->Exception messages-->Define and group exception messages.

      Best regards

      Caetano Almeida

  • Dec 23, 2014 at 06:37 AM

    Hi Suresh,

    Need more details. Is system generating the proposal? Can you provide a screen shot?

    Regards,

    Krishnendu.

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 23, 2014 at 08:29 AM

    Suresh,

    Check your Rescheduling horizon configuration in OMDQ

    Check below SAP Note for detailed information   25388 - MD01, MD02, MD03: Rescheduling proposals: Documentation

    Also check below SAP WIKI for further help with example What is rescheduling and how does it work - ERP Manufacturing (PP) - SCN Wiki

    BR
    KK