To Delete planned costs

Hello All,

I want to know if there is any standard way to delete planned cost? let me tell you that- I have used KP90 and KP91 and  yes it deleted plan cost but it also deleted all CO object including rates which were maintained in KP26.

I need you help to know if there is any Transaction to delete planned cost or planned value which is seen in CJI4(delete plan cost line item) for a particular order, CC or WBS.

Thanks and Regards,

Roshan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Dec 22, 2014 at 06:05 PM

    Hi Roshan,

    Why you want to delete planned cost?  What is the business requirement.

    You can check program RCNCP001 where there is option to delete plan cost data.

    Also refer following SAP note


    779408 - KP90,KP91: What is deleted?

    Regards

    Tushar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Roshan,

      Please use Project version functionality.

      You can save the planned cost in target version for networks or orders for projects

      In report RCNCP001 when you execute, there is checkbox 'Delete Target Version' , set this indicator.

      If you set the indicator, the plan values in the target version are set to zero. Zero records are generated in the database

      Also refer to SAP note 521254 - CJ9D: Indicator 'Delete target version' for more details.

      Regards

      Tushar

  • Dec 24, 2014 at 09:35 AM

    Hi Roshan,

    how you have update plan cost to project object only that is the standard way to delete plan cost from project objects.

    basically plant cost we put to compare plant Vs Actual cost by structure report. so in normal way we modify only plan cost.

    Regards,
    Sanjeev