When I run MD03 for material no. 20187654 in plant no. 1320, I get the below output

The issue is that in the above screenshot, the PR is shown as having Available Quantity of 2 even though a PO has been created for it - the PO is not deleted and has also been invoiced (see below).

I think the issue may be due to the fact that the status is displayed as "RFQ Created" rather than "PO Created" in the above screenshot. However, I am unable to replicate this "RFQ Created" status in my test system - the system moves to "PO Created" as soon as PO is created. Could you please advise why the system shows the PR as having 2 available quantity is MD03?

Any comments on this are welcome.

Regards,

Gaurav Sharma


md03.jpg (114.3 kB)
pr view.jpg (189.2 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Dec 22, 2014 at 10:26 AM

    Dear Gaurav,

    First line is PR created as per the MRP type maintained in the material master, second line item is nothing but dependent reservation.

    While creating production order CO01 then dependent reservation will trigger for bom component.

    Regards,

    Karna J

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 22, 2014 at 09:47 AM

    Hi,

    The Purchase Requisition says it is a third party . Please check the same . May be it would have directly been already directly dispatched to customer .Please check .