BAPI for updating the WBSE Finish Date

Hello Experts,

I am new to SAP Project system Module. I am working on CJ20N Tcode and following is the requirement I am working on currently.

I want to Update WBSE End date , I.E PRTE-PENDE Field . Below is the Screen shot of the Field in the WBSE Header. I need a BAPI through which I can update this (PRTE-PENDE) date field.

Thanks and Regards,

Nikhil Kulkarni

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Dec 22, 2014 at 04:13 AM

    Hi Nikhil,

    Check BAPI BAPI_PROJECT_MAINTAIN

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 22, 2014 at 07:00 AM

    Hi,

    Check if BAPI_PROJECT_MAINTAIN can solve your purpose with the help of your abaper.

    Regads

    Shishir