Progress Controlling with PS

Hello colleagues,

In the moment we are searching for possibilities to measure the progress of our projects in SAP. We are working with detail WBS Structure and networks.

Because of this we plan to use the costs and hours to to generate a progress grade automatically.

Is this possible in the Projectsystem?

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Dec 22, 2014 at 04:16 AM

    Hi Johannes,

    You can achieve it by Progress Analysis

    Progress Analysis - Project System - SAP Library

    As mentioned by Paulo, Measurement Method is a part of Project Analysis

    But in case if you want very simple way of project analysis, you can use CNS41 transaction.

    Regards

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 22, 2014 at 06:25 AM

    Use CNE1/E2/E5 transactions.

    Also read the below threads:

    Progress Tracking - SAP Library

    Regards

    Shishir

    Add comment
    10|10000 characters needed characters exceeded

  • Dec 21, 2014 at 10:06 PM

    Hello Johannes,

    Please refer to below link for possible Progress Measurement Methods:

    Define Measurement Methods - Project System - SAP Library

    What you did mentioned looks similar to Cost Proportionality and Quantity Proportionality.  Besides you can simply use Estimate, that is when the business user does personal estimation in % value.  Sometime that can be most accurate, since not dependent on neither plan nor actual data.

    Automatic is nice, but requires good quality of plan data, as well as proper accruals for actual data.  Your actual cost in the system is normally either behind or ahead of real work progress.

    Regards,

    Paulo

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 22, 2014 at 11:32 AM

    Thank you very much. We will try this.

    BG Johannes