receipt recreate horizon how it works

Dear Expert

we are having Receipt recreate  horizon in product master tab of ATP .how it is deleting already generated planned orders  when  i gone through F1 help below it says that

Definition

Defines a time period behind which receipt elements, created via Capable-to-Promise (CTP) or via a conversion of the ATP tree structure (after a multilevel ATP check) in the order network of the SAP liveCache, are ignored in during a new ATP check.

The time period consists of check date (today's date) and calendar days that you specify in the horizon for re-creating receipts.

Use

You have already performed CTP processing or a conversion of the ATP tree structure (after a multilevel ATP check) and change the sales order in SAP R/3 (SD), for example. If the requirements date (material availability date) is later than the end of the horizon, then the system attempts to ignore the receipt elements created in a previous check (as long as their status allows this), and to create them within a new ATP check.

Dependencies

  • You have set the Recreate Receipts indicator in the check instructions. In Customizing for Advanced Planning and Optimization (APO), choose Global Availability Check (Global ATP Check) -> General Settings -> Maintain Check Instructions.
  • Creating receipt elements again within CTP processing or a conversion of the ATP tree structure (after a multilevel ATP check) is only permitted for make-to-order production. In SAP R/3, make-to-order production can be controlled by means of the requirements type. The requirements type is determined, for example, by means of the MRP group and strategy group in the material master.
  • The receipt elements must have a status that allows deletion.

My question is ;

I have mantained receipt recreate horizon has 0 days in product master

If i create sales order and trigger gatp then I get required Receipt element (planned orders ).AND if i change qty and the requested date in sales order and again Re trigger GATP  I am getting new receipt element then what is use of Receipt recreate horizon  to mantain

thanks in advance

Regards

Virender

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Dec 23, 2014 at 01:11 AM

    ear Expert

    we are having Receipt recreate  horizon in product master tab of ATP .how it is deleting already generated planned orders  when  i gone through F1 help below it says that

    Definition

    Defines a time period behind which receipt elements, created via Capable-to-Promise (CTP) or via a conversion of the ATP tree structure (after a multilevel ATP check) in the order network of the SAP liveCache, are ignored in during a new ATP check.

    The time period consists of check date (today's date) and calendar days that you specify in the horizon for re-creating receipts.

    Use

    You have already performed CTP processing or a conversion of the ATP tree structure (after a multilevel ATP check) and change the sales order in SAP R/3 (SD), for example. If the requirements date (material availability date) is later than the end of the horizon, then the system attempts to ignore the receipt elements created in a previous check (as long as their status allows this), and to create them within a new ATP check.

    Dependencies

    • You have set the Recreate Receipts indicator in the check instructions. In Customizing for Advanced Planning and Optimization (APO), choose Global Availability Check (Global ATP Check) -> General Settings -> Maintain Check Instructions.
    • Creating receipt elements again within CTP processing or a conversion of the ATP tree structure (after a multilevel ATP check) is only permitted for make-to-order production. In SAP R/3, make-to-order production can be controlled by means of the requirements type. The requirements type is determined, for example, by means of the MRP group and strategy group in the material master.
    • The receipt elements must have a status that allows deletion.

    My question is ;

    I have mantained receipt recreate horizon has 0 days in product master

    If i create sales order and trigger gatp then I get required Receipt element (planned orders ).AND if i change qty and the requested date in sales order and again Re trigger GATP  I am getting new receipt element then what is use of Receipt recreate horizon  to mantain

    thanks in advance

    Regards

    Virender

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      ear Expert

      we are having Receipt recreate  horizon in product master tab of ATP .how it is deleting already generated planned orders  when  i gone through F1 help below it says that

      Definition

      Defines a time period behind which receipt elements, created via Capable-to-Promise (CTP)or via a conversion of the ATP tree structure (after a multilevel ATP check) in the order network of the SAP liveCache, are ignored in during a new ATP check.

      The time period consists of check date (today's date) and calendar days that you specify in the horizon for re-creating receipts.

      Use

      You have already performed CTP processing or a conversion of the ATP tree structure (after a multilevel ATP check) and change the sales order in SAP R/3 (SD), for example. If the requirements date (material availability date) is later than the end of the horizon, then the system attempts to ignore the receipt elements created in a previous check (as long as their status allows this), and to create them within a new ATP check.

      Dependencies

      • You have set the Recreate Receipts indicator in the check instructions. In Customizing for Advanced Planning and Optimization (APO), choose Global Availability Check (Global ATP Check) -> General Settings -> Maintain Check Instructions.
      • Creating receipt elements again within CTP processing or a conversion of the ATP tree structure (after a multilevel ATP check) is only permitted for make-to-order production. In SAP R/3, make-to-order production can be controlled by means of the requirements type. The requirements type is determined, for example, by means of the MRP groupand strategy group in the material master.
      • The receipt elements must have a status that allows deletion.

      My question is ;

      I have mantained receipt recreate horizon has 0 days in product master

      If i create sales order and trigger gatp then I get required Receipt element (planned orders ).AND if i change qty and the requested date in sales order and again Re trigger GATP  I am getting new receipt element then what is use of Receipt recreate horizon  to mantain

      thanks in advance

      Regards

      Virender

  • avatar image
    Former Member
    Dec 29, 2014 at 01:07 PM

    I think it is because you have maintained it as "0" days. As the definition in F1 Help says, the purpose of receipt recreate horizon is that behind this horizon orders or receipt elements created are ignored during a new ATP check... I suggest you can test it in the Sandbox or test system - change the values and run checks to see how it is impacting the system... Thereby you will understand it...